Streamlined Procedures for
Incremental Cost Assessment
Introduction
1. The purpose of this note is to set
out streamlined procedures for the estimation of the incremental
costs of GEF projects, and to set these procedures in the context
of the streamlined procedures for GEF operational programming.
2. As set out in the GEF Instrument,1
GEF finances the incremental costs of projects, and has adopted
an approach for estimating them which is set out in a policy paper.2
Streamlined procedures do not introduce any new types of, or
policies for, incremental cost. Rather they show how the approved
approach can be applied pragmatically in different situations
by drawing on lessons of experience. Supplementing these procedures,
there are also case studies and paradigms that can guide Task
Managers in the estimation of the incremental costs eligible for
GEF financing.
3. So far, experience with the application
of the incremental cost approach has taught several things:
- First, sometimes the whole project
(or a clearly identified activity within it) merely complements,
rather than substitutes, existing activities. Where such a project
is required only as a way of meeting global environmental objectives,
a simpler analysis of incremental costs would be appropriate because
the full complexity of the analysis is really only needed where
there is substitution or the generation of additional (non-global)
benefits. Many biodiversity conservation projects, medium size
projects, and small grants proposals could be treated in this
simpler way.
- Second, where the project design
shows more clearly how the project will make a difference to the
global environment, it is easier to estimate the incremental cost.
- Third, when project design and incremental
cost issues have been resolved upstream, the administrative costs
of making any changes needed to conform with the approved GEF
approach are, as expected, lower.
The streamlined procedures are based
on these lessons.
Streamlined Procedures for Operational
Programming
4. The Secretariat and the Implementing
Agencies have already agreed on streamlined procedures for operational
programming. The procedures begin with upstream consultations
on conceptual issues, which can be addressed at relatively low
administrative cost to the Implementing Agencies; progress through
a more detailed bilateral review meeting on project design issues,
which may necessitate some fine-tuning; and finish with the proposal's
inclusion in the Work Program that is presented by the CEO to
Council for their consideration.
5. The streamlined procedures for incremental
cost assessment are elaborations of the operational programming
procedures. Broadly, the procedures, are as follows:
- At the upstream consultations, discussion
of the project concept alone would be sufficient, even without
explicit consideration of any "incremental cost" issues
because getting the strategic fit and the right project design
are what really facilitates subsequent discussion on incremental
cost.
- At the bilateral review meeting,
it would then be necessary to draw out the implications, for incremental
cost, of the decisions taken earlier about project design and
to provide guidance on the steps needed to complete the assessment
satisfactorily.
- At the Work Program stage, the proposal
would be included if the incremental cost estimate was made in
accordance with the guidance given at the bilateral review meeting.
Upstream Consultations on Project
Concept
6. Strategic Fit of the Project
When a project is first considered,
the IA may wish to discuss with the Secretariat certain strategic
issues prior to any discussion of the incremental cost itself
(e.g., how the proposal conforms to one of the Operational Programs,
the short-term criteria, or the operational criteria for Enabling
Activities). This is not only to ensure that the project is eligible,
but also to facilitate subsequent incremental cost discussion
at the Bilateral Meeting. The project must "make a difference"
to the global environment. Use of a project logical framework
would also facilitate discussion.
7. Design of the Project
Activities.
Most projects consist of diverse activities (e.g., training,
investing in alternate pest management, and establishing a national
conservation center). It is useful to identify a small number
of major activities at the outset to make it easier to analyze
the project and, subsequently, to estimate their incremental costs.
Baselines.
Good project design demands that there be a clear understanding
and articulation of the course of events that is threatening the
global environment in order to show that the activities, as proposed,
will reduce or remove the threats. This course of events is often
termed the "baseline," and one would expect that each
activity would be shown to make sense in terms of a baseline that
it was addressing (e.g., the current institutional capacity, food
production and pesticide runoff, and conservation outreach).
Getting these clear at the start will also make it easier to estimate
the extent to which any alternative course of events would cost
more.
Complements and substitutes.
For each activity, it would be necessary to understand whether
it was intended simply to add something without changing the baseline
(e.g., constructing a conservation center) or whether it was intended
to change the baseline by substituting something better (e.g.,
using an appropriate form of integrated pest management as a substitute
for ecologically damaging pesticides). Knowing whether an activity
is complementary or substitutional makes it easier to demonstrate
how it would thereby protect the global environment and why this
would not happen without it, to determine how catalytic the activity
will be, to show any financial leverage, and to estimate the incremental
cost. Note that at this stage this is still just a way of thinking
about the proposed project, the additional effort it may require,
and the extra burden it may impose, not yet a "calculus"
of incremental costs.
8. A typical complementary activity
in biodiversity is a conservation activity that has no direct or major impact on
other economic activities, such as protected area management (gazettal, demarcation, management, conservation centers etc.) and
strengthening of in situ capacity for biodiversity conservation.
(A short illustrative list3 is appended at Annex A. Many of these projects
are in fact small-scale training, capacity-building, institutional strengthening,
or planning activities.) In climate change, one example of a complementary
activity is a module for capacity building in energy planning
that is explicitly required for mitigation scenarios; another
is the removal of a barrier to energy conservation or renewable
energy. In international waters, an illustrative complementary
activity is an end-of-pipe pollution control measure required
only to prevent transborder pollution.
9. A substitutional activity is one
that changes the way of doing business to one that is friendly
to the global environment. Questions one could ask in some situations
to determine whether an activity is a substitute or whether it:
- modifies economic production techniques;
- modifies or substitutes for a regular
development project;
- removes a social or economic cause
of biodiversity loss, provides an alternative livelihood, or substitutes
a renewable energy technology for one that emits GHGs;
- supports planning for an economic
sector (energy, agriculture, forestry, fishing, industry, etc.);
or
- yields economic benefits for the
local population (or for the country as a whole).
10. In biodiversity, substitutional
activities would modify baseline development activities that would
anyway be sustainable in terms of the biological resource of economic
importance (timber, fish, food etc.) to ensure that biodiversity
or its components (habitats, species, or gene pools of
global importance but with little local economic value) would
also be used sustainably. Over time this is likely to facilitate
the transfer of more resources than would be possible with respect
to conservation projects alone. Thus far there are not many GEF
biodiversity projects of this sort, but a short indicative list
is appended at Annex B. The incremental costs would need to be
treated in full with consideration of baseline activities and
alternative that maintains the development goal. If an explicit
cause is identified and the project is in an economic sector (e.g.,
irrigation, cattle grazing pest control in crops etc.) this should
not present any unusual difficulties. In climate change, substitutional
activities are those that provide the same service (e.g., power
or energy) by substituting the supply by one that emits less greenhouse
gas (e.g., renewable energy substituting for fossil fuel energy).
Bilateral Review Meetings
11. The bilateral review can build
on the project design decisions to identify, case-by-case, the
most streamlined way of estimating the incremental cost. Incremental
costs should be considered for each major activity according
to whether that activity is complementary or substitutional.
Typically a project activity that is only complementary will
not require much analysis to justify the incremental cost, but
such projects are less often catalytic and do not leverage financial
resources. A project activity that substitutes for a baseline
course of events will require some further effort to separate
the costs of the baseline from the incremental costs of the proposed
activity, but the activity will have the advantage that it will
thereby leverage funds that would otherwise have gone to finance
that baseline. The following sequence of issues needs addressing.
12. For all activities
Ql.
Is baseline financing secured?
Baseline financing is required. This
is because, in the case of a complementary activity, the baseline
provides the essential context and support, and because, in the
case of a substitutional activity, its full funding requires both
GEF incremental cost financing and non-GEF co-funding equivalent
to the costs of the baseline that would be substituted. For example,
if incremental cost financing is required for the complementary
activity of a commercial tree inventory that is needed to collect
biodiversity data, the whole project would be threatened if the
underlying commercial inventory (baseline) did not proceed for
lack of finance. Or, to take a substitutional example, a solar
energy plant would not go ahead if funds equivalent to the avoided
costs of the fossil fuel alternative were not diverted to the
solar plant.
Q2.
Is the alternative least cost?
The proposed activity is the least cost
way of achieving the identified global environmental benefit.
If a more costly alternative is actually proposed (for other
reasons obviously, such as additional employment generation, a
higher inter-national "profile," etc.) the incremental
cost will be the cost of the lowest cost alternative. If any
activity of the project or activity could conceivably be omitted
without jeopardizing the global environmental objective (e.g.,
the further development of ecotourism once the habitat has been
protected), the incremental cost is the cost of the project without
that activity.
13. For complementary activities
If the activity is deemed to be complementary,
the emphasis will be on establishing this complementarity through
the following questions:
Q3.
What evidence is there that the amount of GEF financing is
genuinely additional, with no crowding out or deleveraging of
other or pre-existing sources taking place? What assurances are
there for the continuance of existing levels of finance from government
agencies or others that have previously financed similar activities
(e.g., national park protection)?
Q4. What cost-sharing with beneficiaries
would be appropriate, and how could cost recovery mechanisms be
built into the project to encourage environmental responsibility
and financial sustainability in the absence of continued GEF support?
Q5. What level of Implementing Agency,
bilateral, private, or NGO co-funding is available in the light
of the benefits enjoyed by the local population or the country
as a whole? A budget would then need to be prepared prior to
Work Program submission.
14. For substitutional activities
If the activity is substitutional, the
emphasis will be on describing and costing the baseline (all the
activities that will be replaced or affected by the project).
Before the project is submitted for the Work Program, a system
boundary that captures all the main effects will need to be described
and an incremental cost matrix will need to be produced in accordance
with the Standard Reporting Format4 of the incremental cost approach.
A decision could also be made about which of the existing "paradigm
cases" is the best model to follow.
Transitional and Follow Up Arrangements
15. The streamlined procedures will
apply to all new project proposals, as described above. Also,
in order to help introduce them rapidly, the Implementing Agencies
may wish to "retro-fit" them to proposals that are currently
being processed.
16. In the spirit of case-by-case pragmatic
application of the incremental cost approach, further guidance
or annexes may be produced later on the basis of experience with
a view to clarifying or streamlining the approach. For example,
further common practices for preparing climate change projects,
international waters projects, and "barrier removal"
projects in all focal areas will be prepared.
Annex A: Typical Complementary
Activities in Biodiversity
Provided they fit strategically in an
Operational Program, follow GEF policies, and are soundly conceived,
the following activities could be regarded as wholly complementary.
Note that it is not so much the type of activity (e.g., training)
that determines whether it is complementary or substitutional,
but the situation.
Institutions and Planning
- Establishing, strengthening, restructuring
or managing a national park or protected area;
- Developing the coordinating, regulatory
or legal frameworks needed to preserve ecological zones;
- Integrating farmer conservation
efforts into national and international gene bank programs;
- Zoning for environmental conservation,
and regional conservation planning;
- Incorporating biodiversity concerns
into national development planning;
- Developing guidelines for sustainable
use (e.g., of forestry products).
Monitoring and Evaluation
- Monitoring environmental conditions
(e.g., community-based monitoring of wildlife populations);
- Undertaking surveys and biodiversity
inventories, and identifying hotspots;
- Developing national environmental
information networks and M&E systems.
Targeted Research
Analyzing habitat and causes of biodiversity
loss.
Education and Outreach
- Providing conservation education
and public awareness of environmental issues (such as developing
public-private partnerships for sustainable development and involving
the community in habitat protection);
- Providing environmental management
fellowships and making twinning arrangements.
Financial Instruments
- Establishing (but not necessarily funding)
a conservation trust fund and testing its feasibility;
- Developing financial strategies.
Demonstrations and Replications
Formulating and testing approaches to
protecting biodiversity, e.g., for controlling exotics.
Annex B: Typical Substitutional
Activities in Biodiversity
For the following substitutional activities,
one would need to:
1. identify the cause of loss of diversity
of biological resources that exists even when natural resources
are used sustainably;
2. design the activity to remove that
cause while maintaining the sustainable development purpose
(Note: All these activities will make a "difference"
through alternatives, changing, reducing etc.); and
3. estimate the incremental cost is
the difference in the cost between the baseline and proposed alternative,
according to the approved approach.
- Reducing pesticide runoff threatening
an important wetland habitat, by using more costly natural pest
control methods;
- Reducing industrial pollution of
a national park, through more costly pollution control methods;
- Reducing irrigation water abstraction
(e.g., to maintain a wetland habitat or to remain within groundwater
recharge limits). Irrigation is usually practised where there
are large rivers and lakes, since groundwater is scarce and often
saline;
- Changing sustainable logging practices
to protect habitat of a species;
- Substituting environmentally friendly
subsistence fishing to prevent danger to endemic species of fish;
- Removing the incentives for the
introduction of exotic species by simultaneously raising productivity
of indigenous species and maintaining restrictions;
- Introducing new fish traps to maintain
fish catches while preventing the trapping of (inedible) species
of high biodiversity value;
- Relocating a plant (industrial,
sewage, etc.) to prevent discharges into an ecologically sensitive
area;
- Changing water resource use and
distribution patterns that would even out grazing pressure and
prevent deterioration of vegetation;
- Modifying a wildlife ranching system
so that it is compatible with biodiversity conservation;
- Changing already sustainable livestock
management and grazing patterns specifically to protect biodiversity;
- Altering intensified production
techniques to prevent "land mining";
- Making sustainable the provision
of other services and industries that use biological or ecological
resources (such as ecotourism and microproduction); and
- Conserving rural energy (or switching
to an alternative renewable supply) in order to conserve natural
vegetation that, from a biodiversity perspective, is important
as habitat or in its own right;
- Improving research facilities to
enable them to manage biodiversity collections and data;
- Providing alternative income opportunities.
Endnotes
1Instrument,para. 2.
2GEF/C.7/Inf.5
3Note that the annexes are illustrative only, and list the projects
typically meeting the criteria for being complementary or substitutional.
Proposals must be considered case by case.
4GEF/C.7/Inf., annex.
return to top